Step 1
On the 鈥楩unction Menu鈥�
- select 鈥楢pplication鈥� on the toolbar
- select 鈥楥hange of Circumstances鈥� from the options available. You will be taken to the 鈥楰ey Entry Data鈥� screen
- enter the customer鈥檚 NINO
- select 鈥極K鈥�. You will be taken to the 鈥楢pplicant Details鈥� screen
Note: If the 鈥楽ignals鈥� box displays select 鈥極K鈥� or 鈥楥ancel鈥� to clear.
- select 鈥楥h鈥� on the toolbar, you will be taken to 鈥楥hild Details鈥� screen
- click on the relevant child or young person to highlight them.
If there is a responsibility end date shown and it is earlier than the relevant dates, treat the child or young person or young person as not included in the award.
If there is a responsibility end date shown and it is later than the relevant dates, go to Step 2.
If there isn鈥檛 a responsibility end date shown, go to Step 2.
Step 2
Check responsibility dates
- select the name of the relevant child or young person
- select 鈥楥orrection鈥�, you will be taken to the 鈥楥orrection Child鈥� screen
- select the 鈥楻esponsibility History鈥� check box to tick it
- select 鈥楬istory鈥�, if you receive the warning message 鈥楢re you sure date of responsibility is not required?鈥�
- select 鈥榊es鈥�.
If you are taken directly to the History screen without a warning message
- make a note of the dates shown in the 鈥業nclude From Date鈥� and 鈥楨nd Date鈥� fields
Note: If more than one set of dates are shown make a note of all the dates displayed.
- select 鈥楥ancel鈥�, you will be returned to the 鈥楥orrection Child鈥� screen
- go to Step 3.
If you receive the warning message 鈥楥hild is over 16. You must enter an Education or Connexions start date鈥� or 鈥楥hild is over 19 you must enter an education start date鈥�
- select 鈥極K鈥�, you will be taken to the 鈥楬istory鈥� screen
- make a note of the dates shown in the 鈥業nclude From Date鈥� and 鈥楨nd Date鈥� fields
Note: If more than one set of dates are shown make a note of all the dates displayed.
- select 鈥楥ancel鈥�, you will be returned to the 鈥楥orrection Child鈥� screen
- go to Step 5.
Step 3
If the child is under 16 or the young person is 16 and the relevant date you are checking is prior to 1 September following their 16th birthday, go to Step 4.
If the young person is older than 16 or they are 16 and the relevant date you are checking is after 1 September following their 16th birthday, go to Step 5.
Step 4
The child or young person will have been included in the award from the responsibility include from date or the effective date of the claim whichever is the most recent.
If there is an end date present, the child or young person will have stopped being included in the award from the end date shown.
If there is more than one period of responsibility
- the child or young person will have been included in the award previously from the 鈥業nclude From鈥� date or the effective date of the claim, whichever is the most recent
and
- the child or young person will have stopped being included in the award previously from the 鈥楨nd Date鈥�.
Step 5
Check if the 鈥楩TE History鈥� check box is enabled.
Note: The box is enabled when it is shown in white and not greyed out.
If the box isn鈥檛 enabled, go to Step 7.
If the box is enabled
- select the 鈥楩TE History鈥� checkbox
- select 鈥楬istory鈥�
- go to Step 6.
Step 6
Note: The message 鈥楢re you sure date of responsibility is not required?鈥� may display. If so, select 鈥榊es鈥�.
If you receive either of the warning messages 鈥楥hild is over 16. You must enter an Education or Connexions start date鈥� or 鈥楥hild is over 19 you must enter an education start date鈥�
- select 鈥極K鈥�, you will be taken to the 鈥楬istory鈥� screen
- make a note of the dates shown in the 鈥業nclude From Date鈥� and 鈥楨nd Date鈥� fields
Note: If more than one set of dates are shown make a note of all the dates displayed.
- select 鈥楥ancel鈥�, you will be returned to the 鈥楥orrection Child鈥� screen
- go to Step 7.
If you are taken directly to the 鈥楬istory鈥� screen without receiving a warning message
- make a note of the dates shown in the 鈥業nclude From Date鈥� and 鈥楨nd Date鈥� fields
Note: If more than one set of dates are shown make a note of all the dates displayed.
- select 鈥楥ancel鈥�, you will be returned to the 鈥楥orrection Child鈥� screen
- go to Step 7.
Step 7
Check if the 鈥楥onnexions History鈥� check box is enabled.
Note: The box is enabled when it is shown in white and not greyed out.
If the box isn鈥檛 enabled, go to Step 9.
If the box is enabled
- select the 鈥楥onnexions History鈥� check box
- select 鈥楬istory鈥�
- go to Step 8.
Step 8
Note: The message 鈥楢re you sure date of responsibility is not required?鈥� may display. If so, select 鈥榊es鈥�.
If you receive either of the warning messages 鈥楥hild is over 16. You must enter an Education or Connexions start date鈥� or 鈥楥hild is over 19 you must enter an education start date鈥�
- select 鈥極K鈥�, you will be taken to the 鈥楬istory鈥� screen
- make a note of the dates shown in the 鈥業nclude From Date鈥� and 鈥楨nd Date鈥� fields
Note: If more than one set of dates are shown make a note of all the dates displayed.
- select 鈥楥ancel鈥�, you will be returned to the 鈥楥orrection Child鈥� screen
- go to Step 9.
If you are taken directly to the 鈥楬istory鈥� screen without receiving a warning message
- make a note of the dates shown in the 鈥業nclude From Date鈥� and 鈥楨nd Date鈥� fields
Note: If more than one set of dates are shown make a note of all the dates displayed.
- select 鈥楥ancel鈥�, you will be returned to the 鈥楥orrection Child鈥� screen
- go to Step 9.
Step 9
In order for the young person to be included in the award there must be FTE or Connexions dates present otherwise they will cease to be included in an award from 1 September following their 16th birthday.
If either the FTE or Connexions include from date is after 1 September following the young person鈥檚 16th birthday, there will be a gap during which time the young person will not have been included in the award
For example: If the young person was 16 on 25/03/2009 and there is an FTE include from date of 10/11/2009 the young person will not have been included in the award from 01/09/2009 to 09/11/2009.
If there are end dates for FTE or Connexions followed by further include from dates and these dates are not consecutive, the young person will not be included in the award for any dates between the end date of one and the subsequent include from date of the other.
If for any period there is a gap in the Responsibility period where a responsibility end date has been entered and then at a later date another responsibility include from date has been entered
- the young person will not be included in the award for this period
- this will apply even if this period is covered by dates entered in the FTE or Connexions include from field.
For example: If there is an FTE include from date of 01/09/2009 and no end date present but there is a Responsibility end date of 12/10/2009 and then a subsequent Responsibility include from date of 11/01/2010, the young person will not have been included in the award from 13/10/2009 to 10/01/2010.
If there is a Responsibility end date present and no subsequent Responsibility include from date, the young person will have stopped being included in the award from the Responsibility end date irrespective of any FTE or Connexions dates present.